Logistics Center Bayern

Logistics Center Bayern

Die Abbildung zeigt das Logo von Schulz - Gebäudetechnik in Bestform
Die Abbildung zeigt das Logo von Schulz - Gebäudetechnik in Bestform

The order

Uninterrupted and trouble-free installation of a new lighting system in a 5,600 m² logistics area - back to back with employees in a very confined space.

 

The challenge

Fault-free installation is one thing - leaving the old lighting system in place until the order is completed is another. But how else is regular operation to be maintained? At least not if drilling causes dust and dirt. In addition, work is made more difficult because the hall ceiling is full of steel cables and suspensions, and pipes as well as supply networks block exit routes. A case for Schulz in top form.

 

The solution

The use of a comparatively small and narrow electric working platform guarantees regular operation at the job site in the simplest way. Everything continues as usual, no harmful exhaust gases are produced, and the work processes in the hall are hardly disturbed despite Schulz's presence: the assembly of the new lighting system is underway.

Work in particularly busy areas is postponed to break times. And in order to work dust-free, we use specially developed covers in addition to the standard vacuum cleaner we use and install them at the respective place of use.